Students are headed back to school next week in the Belmont-Redwood Shores Elementary School District after the completion of a $54 million building and modernization project wrapped up this week.
School will begin on Wednesday, Sept. 11, because of the construction, but the project was on time and on budget, said Superintendent Michael Milliken, noting that it has been a bit of a child-care crunch.
“The school year is also going to end three weeks later,” Milliken said. “But all these kids are effectively going to be walking into new schools and I’m very excited. We didn’t want to have construction going on simultaneously with classes.”
Six of the seven district sites underwent a major 10-week modernization program this summer, with nearly 250,000 square feet of updates. There was also construction during the summer of 2012, so the total facilities upgrade has been going on for the past 16 months. The district added 28 classrooms to address enrollment growth and there were more than 400-500 tradesmen working daily at the sites.
“It is a marvel and an accomplishment to get this much work done so quickly,” Nellie Hungerford, assistant superintendent of business services and operations, wrote in an email. “I celebrate the amazing work of Blach Construction and Lionakis Architects.”
Recommended for you
Two bonds worth $60 million provided funds for the classroom upgrades. Redwood Shores Elementary School was the only school that went untouched this year since it was just built in 2010. Last summer, the school did add six classrooms, a bike rack and a brand-new playground, along with improved bike access to the school.
“There is a little teacher anxiety since they’ve been kept off campus until today,” Milliken said. “The deadline for them to prepare for school is today to Tuesday and the first day of school is Wednesday, so there’s not a lot of wiggle room.”
Keep the discussion civilized. Absolutely NO
personal attacks or insults directed toward writers, nor others who
make comments. Keep it clean. Please avoid obscene, vulgar, lewd,
racist or sexually-oriented language. Don't threaten. Threats of harming another
person will not be tolerated. Be truthful. Don't knowingly lie about anyone
or anything. Be proactive. Use the 'Report' link on
each comment to let us know of abusive posts. PLEASE TURN OFF YOUR CAPS LOCK. Anyone violating these rules will be issued a
warning. After the warning, comment privileges can be
revoked.
Please purchase a Premium Subscription to continue reading.
To continue, please log in, or sign up for a new account.
We offer one free story view per month. If you register for an account, you will get two additional story views. After those three total views, we ask that you support us with a subscription.
A subscription to our digital content is so much more than just access to our valuable content. It means you’re helping to support a local community institution that has, from its very start, supported the betterment of our society. Thank you very much!
(0) comments
Welcome to the discussion.
Log In
Keep the discussion civilized. Absolutely NO personal attacks or insults directed toward writers, nor others who make comments.
Keep it clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
Don't threaten. Threats of harming another person will not be tolerated.
Be truthful. Don't knowingly lie about anyone or anything.
Be proactive. Use the 'Report' link on each comment to let us know of abusive posts.
PLEASE TURN OFF YOUR CAPS LOCK.
Anyone violating these rules will be issued a warning. After the warning, comment privileges can be revoked.